CAL Green requires x number of EVSE per xxx number of spaces - each on its own 40 amp circuit. Some dual EVSE are on a single 40 amp circuit and split the 40 amp. Does this mean that half of those plugs don't comply with the required number?

RESPONSE: The California Green Code appears to require service panels, sub-panels, and raceway of sufficient capacity to accommodate 40 amp circuits rather than mandating one 40 amp circuit for each EVCS in residential and nonresidential locations. For additional information you may contact the Department of Housing and Community Development for infrastructure requirements at residential locations or the Building Standards Commission for infrastructure requirements at nonresidential locations.