Questions & Answers: Supplement to the 2013 DOJ/DOT Joint Technical Assistance on the Title II of the ADA Requirements To Provide Curb Ramps when Streets, Roads, or Highways are Altered through Resurfacing
Q6: Is the curb ramp installation work required to be a part of the Plans, Specifications and Estimate package for an alteration project or can the curb ramp work be accomplished under a separate contract?
A6: The curb ramp installation work can be contracted separately, but the work must be coordinated such that the curb ramp work is completed prior to, or at the same time as, the completion of the rest of the alteration work. See 28 CFR 35.151(i).