Costs and Personnel Time for Beach Path Installation
The following summary of costs and time estimates is not meant to be definitive but to document data for the beach path installation.
Quantity of material
EWF 6 yd3
Vitri-Turf 15 gal
Soil-Sement 35 gal (45% solids)
Market value of material
EWF $21/yd uncompacted (includes shipping) $126
Vitri-Turf $18/gal (100% solids, 11 lb/gal) 270
Soil-Sement $7/gal (45% solids, 9 lb/gal) 245
Drainage system Geotextile 80
$721
Equipment and tool rental (market value) $100
Personnel time
Base prep and geotextile installation, 4 h @ $10/h $40
Bonded surface install, 16 h @ $15/h 240
The installation of the two surface treatments was completed during one workday. Approximate efforts for the installation of 200 ft2 of each material (400 ft2 total) were 16 h (4 people for 4 h).
Summary of costs for beach path surface
Cost ($/ft2) | |||
Binder | Labor | Materials | Surface w/labor |
Vitri-turf (38 mm, 1.5 in.) | 0.70 | 1.87 | 2.57 |
Soil-Sement (63.5 mm, 2.5 in.) | 0.70 | 1.74 | 2.44 |
User Comments/Questions