There is some confusion about whether the “accessible path” that is required means there must be an accessible path from the EVSE (charger) to the facility/building at which the station is installed, or whether the accessible path is just from the parking spot to the EVSE (charger). If the prior is enforced, it could increase the costs of installing EVSE in some instances. What is the correct interpretation of “accessible path”?
RESPONSE: The term used in the CBC is “accessible route.” EVCS required by CBC Chapter 11B to be accessible must have both, an accessible route to the facility entrance (see CBC Section 11B-812.5.1) and an accessible route from the vehicle space to the EVSE (see CBC Section 11B-812.5.2).